Dunno

From the Haynes:
Coil - testing 2
1 The coil is located on the bulkhead under
the plenum chamber (see illustration). It
should be periodically wiped clean to prevent
HT voltage loss through possible arcing.
2 To ensure that the correct HT polarity at the
spark plugs, the coil LT leads must always be
connected correctly. The ignition lead from
the fusebox must be connected to the
positive (+) terminal 15, and the distributor
lead (usually green) must be connected to the
negative (-) terminal 1. Incorrect connections
can cause bad starting, misfiring, and short
spark plug life.
3 Complete testing of the coil requires special
equipment. However, if an ohmmeter is
available, the primary and secondary winding
resistances can be checked and compared
with those specified. During testing, the LT
and HT wires must be disconnected from the
coil.
4 To test the primary winding, connect the
ohmmeter between the two LT terminals. To
test the secondary winding, connect the
ohmmeter between the negative (-) terminal 1
and the HT terminal.