« Reply #56 on: 10 February 2021, 15:46 »
Maybe one of those items has no on hand availability date yet but as I said before, you won't get a "build date confirmed" until 4 weeks before the planned build date.
And you won't get the planned build slot until every part is predictred as available and there is a slot on the production line.
This is how Just in Time (JIT) manufacturing works. Its a concept created by Toyota originally but one used since then by anyone doing manufacturing of anything - like my employer...
Volkswagen works more on a When We Get Round To It (WWGRTI) system which can be anything from a few weeks if you order through the fleet department to 12 months plus if you’re coughing up your own cash through retail.

Logged
‘23 8R, ‘20 8CS, ‘19 135iX, ‘19 TCR, ‘17 Ed40, ‘17 GTD, ‘15 7R, ‘13 GTI PP, ‘11 GTI, ‘09 GTI, ‘98 Ibiza Cupra, ‘05 GTI, ‘06 Polo GTI, ‘04 GT TDI, ‘05 Fabia vRS, ‘02 GTI T, ‘03 Ibiza TDI 130, ‘01 Leon 180, ‘89 mk2 16v, ‘99 Ibiza TDI, ‘96 VR6, ‘98 Ibiza TDI, ‘92 VR6, ‘88 mk2 8v, ‘92 Polo G40, ‘91 mk2 8v, ‘89 mk2 8v, 205 GTI 1.9, ‘83 mk1 GTI, ‘80 Scirocco GTI, plus some others I’ve forgotten